REPAIR AND REHABILITATION OF A FLOORING SETTLEMENT

CONSTRUCTION PROGRESS
STEPS INVOLVED

1.     Existing Floor Levels marked in the existing wall.
2.     Existing tiles removed.
3.     Existing P.C.C removed.
4.     Existing soil removed.
5.     Checked the Flooring room length is not more that 10'0" and fixed the location if not.
6.     We found some half brick walls resting on PCC existing flooring concrete.
7.     Made Sand filling and PCC below the half Brick wall.
8.     Made the grade beam.
9.     Construct the Brick wall till the bottom Half Brick wall.
10. Plastering done in the basement Brick wall.
11. After curing the Wall plaster 3days the excavated earth filled in that basement
12. The earth filling taken by two layer and compacted with water.
13. After two days the 1'0" sand filled in the required level and compacted with poured water.
14. Structural steel Frame 2 1/2" x 1 1/2" fixed in Brick wall with 12mm anchor bolt.
15. 4" thick P.C.C laid over the filled sand.
16. Reinforcement Bar Fe500,8mm @ 6"c/c (both ways) mesh prepared over the frame.
17. Placed the 20mm thick cover Block in below mesh.
18. M20 grade concrete poured and made the grade slab with well manual compaction.
19. After 21 days curing of grade slab , Tile flooring started with Vitrified 2'0" x 2'0" Marbonite tiles
20. After tile finishing, Skirting tile laid and Painted work started and completed.